Skip to main content

Critical Lift Plan

Critical Lift Plan

Lifting heavy loads with cranes demands precision and safety, especially for critical lifts exceeding 75% of a crane’s capacity. Here, I want to share a few key factors, like load weight, rigging, lift radius, boom angle, and crane stability, and how they are calculated to ensure safe execution, with adjustments.

Below is the process and adjustable parameters, emphasizing the need for professional oversight.

Gross Load Calculation

Load Weight: 188,000 lb (94 US tons)
Rigging Weight: 1,100 lb (0.55 US tons, slings/chains)
Hook Weight: 660 lb (0.33 US tons, from crane specs)
Gross Load: 188,000 + 1,100 + 660 = 189,760 lb (94.88 US tons)

Lift Geometry

Lift Radius: 49.2 ft (center of crane to load center)
Lift Height: 65.6 ft (ground to top, including load + clearance)
Minimum Boom Length: √(49.2² + 65.6²) = √(2420.64 + 4303.36) = √6724 ≈ 82 ft
Selected Boom Length: 98.4 ft (30 m, for margin)
Boom Angle: acos(49.2 / 98.4) = acos(0.5) = 60° (from horizontal)

Crane Capacity Check

Rated Capacity: 300,000 lb (150 US tons, from load chart, 98.4 ft boom, 49.2 ft radius, ~60°)
Utilization: (189,760 / 300,000) × 100 = 63.25%
Critical Lift Threshold: >75% → not critical, but a plan is required for heavy load

Safety Adjustments

Wind Derating: 20% reduction if wind >22 mph; 300,000 × 0.8 = 240,000 lb (120 US tons)
Adjusted Utilization: (189,760 / 240,000) × 100 = 79.07% (critical, >75%)
Mitigation: Increase radius or select a higher-capacity crane

Stability Check

Load Moment: 189,760 × 49.2 = 9,336,192 lb-ft
Tipping Moment: 6,500,000 lb-ft (crane specs)
Stability: 9,336,192 > 6,500,000 → unstable, requires counterweights or larger crane

Adjustable Factors

Load/rigging/hook weights: Reduce to a lower gross load.
Radius/height: Increase radius to reduce moment and utilization (per load chart).
Boom length/angle: Extend for better capacity at radius.
Environmental: Account for wind/ground conditions → derate capacity.

Crane specs: Upgrade to a higher-capacity crane or add counterweights for stability.

Advice

Always engage a licensed engineer or use certified software (e.g., crane simulation tools) to perform calculations, ensuring all criteria like soil bearing, dynamic loads, and regulations are accounted for safety and compliance.

Lift is critical (79.07% > 75% under wind conditions). Unstable (moment 9,336,192 lb-ft > 6,500,000 lb-ft). Adjust radius, add counterweights, or use a higher-capacity crane. Verify with load charts and the engineer for site-specific factors.

Comments

Popular posts from this blog

Great Man-Made River (GMR)

Libya's Great Man Made River: The Great Man-Made River in Libya is one of the most ambitious Civil Engineering Project in history of mankind.  In the year 1953, the Libya Government found out not only vast oil reserves but also vast quantity of fresh water locked under the strata, most of the water was trapped around 7000-30000 years ago which is divided in 4 different basins. The first basin is named Kufra basin which is neat Egypt Border which covers almost 35000 sq kilometer which is quite deep around 2000 m deep. The other basin is in Sirte Basin which cover 10000 sq kilometer, third in Murzuk Basin and the last in Jabal Fezzan Basin covering 4800 sq kilometers area.  The GMR project will be used to transfer water to North of the country to provide water for irrigation purpose for more than 6 million  people. This will be a changing point  for Libya and the Colonel Muammar Gaddafi called it the Eighth Wonder of World. The work started in 1984 of the project and e...